AI Financials

IREN Ltd

IRENpublicneocloud

Power-first data centers / GPU cloud

Australian-headquartered operator converting bitcoin-mining sites with contracted power in the United States and Canada into GPU cloud and AI data-center capacity, funded largely through convertible notes. Reported under IFRS through fiscal 2024 and under US GAAP since fiscal 2025; fiscal year ends June 30.

CAPEX in 2025
$1.0B
— on the year before, not all four · four calendar quarters, each as the company reported it
how it is counted

cash purchases of property and equipment in the calendar quarter, as the company's own cash-flow statement reports it. The year: the newest calendar year whose fourth quarter at least 90 % of filers have reported; a filer counts only if it reported all four quarters.

Four quarters, 2025 Q3 – 2026 Q2 →+423.2% on the four before, $0.6B — its line in the Overview's league
how it is counted

per filer: the same four quarters, the four before them and the change; null where the filer did not report all four

$3.0B
Newest quarter · 2026 Q2— of revenue · +622.3% on a year before
how it is counted

Of revenue: the quarter's CAPEX as a share of the same quarter's revenue, where the company reports both. On a year before: the change on the same calendar quarter a year before, where the filer reported both.

$1.33B
Off the balance sheet →what it owes that its balance sheet does not carry, each fact counted once · verified 2026-09-28
$200M
Notes priced since 2024 →each tranche in the ledger as the company itself states it
—
Loans and credit facilities →new facilities as signed, from the company's own announcements
$1.5B
Debt due in 12 months →the company's own five-year schedule
$177M
Documents in the corpusthe company's own reports, announcements and earnings calls that the rules read
47

CAPEX by quarter

Cash purchases of property & equipment (cash-flow statement), on calendar quarters, each from the company's own reports; hover a bar for revenue, its share and the change on a year before. How CAPEX is read →

Quarters since 2022 Q4, as reported

8 rows
cash purchases of property and equipment in the calendar quarter, as the company's own cash-flow statement reports it. Each quarter is the three months as the company reports them, or its year-to-date figure less the one before. The site shows the quarters since 2022 Q4; the pipeline holds 8 of IREN's.
2026 Q2$1.33B——+622.3%
2026 Q1$949M——+559.0%
2025 Q4$540M——+288.5%
2025 Q3$180M——+69.8%
2025 Q2$184M———
2025 Q1$144M———
2024 Q4$139M———
2024 Q3$106M———
australianeocloudpowerGPU-cloudconvertiblespublicperiphery